top of page

Ithaka

Scope of Work: 16,000 sq ft of glue removal and 400 grit polish.

Schedule: 15 days to complete

Actual duration: 12 days

The Ithaka project in Princeton, NJ is an office restoration project. The client contracted with a vendor to dismantle and remove all cubicles and office furniture. Scrape the carpet and prepare the space to be polished.Surface Solutions was contracted to quickly grind and polish the space to a 400 grit finish. The employees were moved out for no more than 3 weeks in order to complete the project. 

Project was completed with 2 grinders and a 5 man team.